Do you need a permit to install an EV charger in San José?
For a Level 2 (240-volt) charger, yes. The City of San José requires an electrical permit, and a mechanical permit too if the manufacturer specifies mechanical ventilation. A Level 1 charger on a standard outlet needs no permit.1
CSLB #1050108 · Licensed, bonded and insured

The short version
How the EV charger permit works
The City's own steps, in order.1
Pick the level
Level 1 uses a standard 120-volt outlet. Level 2 uses a 240-volt outlet.
Check the panel and the circuit
Write down the panel rating of the existing service, for example 200 amps, the charger's load, and the circuit size. These go to the inspector.
Apply online
Single-family and duplex homes: go to SJPermits.org and use the Application Wizard. One application can secure more than one permit. The system shows the fee, you pay online, and you download the Permit Card.
Install to code
Wiring and any panel upgrade must follow the current California Electrical Code. Place the charger and utility panel as the manufacturer's written guidelines say.
Inspect
The permit card lists the inspections. Schedule them at SJPermits.org or call 408-535-3555. Have the charger's UL listing number ready. See our inspection scheduling guide.
Load, panel and what the inspector wants
- Continuous load, 125 percent
- EV charging loads are continuous. Overcurrent protection for the feeders and branch circuits must be rated at least 125 percent of the equipment's maximum load, under California Electrical Code Article 625.41.1 For example, a charger that draws 32 amps at full load needs a circuit rated for at least 40 amps.
- Load calculation
- If the service panel is rated 125 amps or less, you must provide a load calculation that includes 125 percent of the maximum EV charging load.1
- Panel upgrade
- The City page sets no minimum panel size for a charger. Any electrical panel upgrade and wiring must conform to the current California Electrical Code. If the calculation shows the panel is too tight, see electrical panel upgrades in San José.1
- UL listing
- At inspection, provide the charger's UL listing number, or the listing number of another approved nationally recognized testing laboratory, in compliance with UL 2202, the standard for electric vehicle charging system equipment.1
- Second meter
- Tell the inspector if a second electric meter will be installed for special utility rates for EV charging.1
- Condos and townhomes
- Apply at SJPermits.org only if the charger is in an assigned parking space. Other multifamily installs follow the City's commercial EV charging process. If a rated assembly will be penetrated, have the rated penetration details ready for the inspector.1
Adding an EV charger? We handle the permit and the work.
Tell us about the house and the charger. We check the panel, pull the electrical permit and schedule the inspection through final.
- The city and the age of the house
- The charger you picked, or the car
- Where the panel and the parking spot are
Prefer to talk? Call (408) 667-4946 or send a text. Office hours: Monday to Friday, 7 am to 3 pm.
- CSLB #1050108
- Licensed, bonded and insured
- 1-year labor warranty
- BBB A+ rating
David and Tristan, the owners, stay involved from the first walkthrough to the final check. We reply the same business day, Monday to Friday.
Do I need a permit to install an EV charger in San Jose?
Can I install a fast charger at my house?
Will I need a panel upgrade for an EV charger?
What does the inspector ask for?
How do I apply, and what about a condo or townhome?
Sources
This page explains the City's published rules for residential EV charger permits. The City decides what applies to your property. Check the City page for current details.